docs: add a piechart with stages

This commit is contained in:
Igor Mandrigin 2020-08-05 10:29:15 +02:00
parent 0514501937
commit 8b5903f6f2
2 changed files with 8 additions and 0 deletions

Binary file not shown.

After

Width:  |  Height:  |  Size: 200 KiB

View File

@ -22,6 +22,14 @@ If the app is restarted in between stages, it restarts from the first stage.
If the app is restared in the middle of the stage execution, it restarts from that stage, giving it the opportunity to complete.
### How long do the stages take?
Here is a pie chart showing the proportional time spent on each stage (it was
taken from the full sync). It is by all means just an estimation, but it gives
an idea.
![](/docs/stagedsync_proportions.png)
## Reorgs / Unwinds
Sometimes the chain makes a reorg and we need to "undo" some parts of our sync.